Case Study St Dismas Medical Center

Practices in Project Management: The St. Dismas Medical Center

4115 WordsSep 5th, 201417 Pages

Practices in Project Management
MSPM 6102
April 25, 2014
Abstract
The St. Dismas Medical Center (SDMC) Assisted Living Facility (ALF) Project was authorized to create a new service line to counteract a decline of inpatient activity. The project objectives are to build 100 light- and heavy-assist units in a standalone residential facility with a sheltered connection to SDMC by late-July 2001 and within an $11 million budget.
The particular deliverables, constraints, assumptions, exclusions, and work breakdown structure are outlined in the Project Scope Statement. Brainstorming and scenario analysis will be used in the risk strategy, while cost-benefit analysis will be the primary tool in project quality management. A…show more content…

Assumptions and Constraints
The following is assumed:
Project funds will be released in a timely manner.
Project team members and resources will be available as needed.
Contractors will have the skills and experience needed to complete the project.
The constraints are as follows:
The construction cannot begin until after the November 1999 city elections.
The facility needs to open by late July 2001.
Operational and administrative policies, procedures, and systems need to be created and regulations and standards need identification.
High-Level Risks As with all projects, there is a risk of running over budget, over schedule, and/or falling short on scope. There are several high-level risks for the ALF project. One particular area of concern was the short seven-month time period for the complex construction project, but that has been extended about another year. Further, the organizational complexity is high with the number of people involved across many functions and the decision-making body being the Board of Trustees. This complexity may lead to delays in decision-making.
The project is also much larger than SDMC has handled in the past with only one team member having construction experience. The operational and administrative regulations and standards for construction and healthcare industries will be complex and have not yet been identified. Construction projects have a strong potential to impact

Show More

Similar Documents

St. Francis College Case Study

... Ateneo de Davao University In Partial Fulfillment of the Requirements in Communication Arts MA 300 Full Written Analysis of the Case on St. Francis College of Commerce Analine R. Evangelista Kristel Mae D. Magsipoc Hadriza S. Omar Juella M. Laguna September 22, 2012 I. Summary St. Francis University was a medium-sized private University, located in a major port city in Visayas. The University is well known for its engineering and Science degree courses and was one of the better private universities in the city. It boasts of a total of 26,000 enrollees at both the graduate and undergraduate levels. The College of Commerce was a major unit of the University. However, it has only 3000 student enrollees or so, compared to the College of Engineering, which accounted for more than a third of the University’s enrollment. The College of Commerce has 55 full time faculty and over 100 lecturers. The faculty members taught as many as 5 courses per semester while the lecturers taught three courses. The College of Commerce was distributed among the four major fields, namely: Banking and Finance, Accounting, Marketing and Business Management. In June of 1988, Mr. Santos assumed the position of Dean of the College of Commerce. Since the college experienced rapid growth in enrollment in the University during the past ten years, Dean Santos wanted to combine curricular improvements and administrative changes that would......

Words: 2550 - Pages: 11

St. Dismas Assignment # 3

...1. Draw a Gantt chart for the construction phase of the program. What is the completion date if construction starts in March? What is the completion date of the project if construction is started in November? If the project is started on March 1st, 2012, the finish date is July 30th, 2013. For the November start date, the case does not mention exactly what date the project should start but rather mentions that it should start after the elections. We do not have the election date so I will assume a start date of November 14th, 2011, which is a Monday. In this case, the end date of the project would be April 11th, 2013. However, the case states that if the project starts in November, bad weather could affect the outside operations, adding as much as 2 months to the duration. If we add 2 months to phase 1, the entire project is delayed 2 months. However, if the delay only occurs in phase 2, than the end date of the project would not be affected since no tasks have phase 2 as a predecessor. This is quite unlikely since it would impossible, in real life, to proceed to phases 3 and 4 (Enclosures and Interiors) without first completing or at least having a certain percentage completed of phase 2 (Structure). For this reason, I choose to add 2 months in phase 1 and therefore have a new end date of July 4th, 2013. Please note that I have also considered that the 2 months delay include the Christmas and New Year holidays. Gantt charts of both start......

Words: 633 - Pages: 3

Overview of Assisted Living Facilities

...Abstract Assisted living is a fairly new and unique part of the long term care continuum of services. The goal of assisted living is to maximize the independence of older adults while living in a homelike environment. This paper will provide an overview of assisted living facilities including the number of facilities and residents, costs, services, and growth expectations. Challenges with oversight and regulations will be discussed as well as solutions to the problem. Challenges and solutions for staffing and training issues will also be discussed. The paper will also highlight “In Loving Hands Assisted Living” which is a local assisted living facility that I called and visited to aid in my research. I will give an overview of the Fort Washington area in terms of older adults and the long term care market. The challenges with this provider are marketing and staffing for which I suggest low cost advertisement and comprehensive staffing patterns. Lastly, a conclusion and summary are provided for the current state and future of assisted living facilities. Overview of Assisted Living While the definition of assisted living facilities vary from state to state, this type of facility is generally defined as “a housing option that involves the delivery of professionally managed, supportive services and depending on state regulations, nursing services in a group setting that is residential in character and appearance” (Evashwick, 2005, p 152). ......

Words: 3356 - Pages: 14

St. Dismas

...St. Dismas Medical Center, an urban, nonprofit, 450-bed rehabilitation hospital began to see a significant decline in admissions. St. Dismas's mission focuses on inpatient and outpatient rehabilitation of the severely injured and catastrophically ill. While the patient census varied from month to month, it appeared to the St. Dismas Board of Trustees that the inpatient population was slowly but steadily declining. The hospital's market researchers reported that fewer people were being severely injured due to the significance of seat belts and bicycle/motorcycle helmets. In order to get a handle on the future of the organization, the Board, and the CEO, Fred Splient M.D. called for a major strategic planning effort to take place. In January 1999, St. Dismas held a planning retreat to identify future opportunities for the hospital. The outcome of the retreat was that the Medical Center needed to focus its efforts around two major strategic plans. The first, a short-run initiative, was to be more cost-effective in the delivery of inpatient care. The second, a long-run strategy was to develop new programs and services that would capitalize on the existing, highly competent rehabilitation therapy staff, and St. Dismas's excellent reputation in the region. At the time of the retreat, Fred Splient’s parents were living with him and his family. Fred was an active member of the “sandwich generation.” His parents were aging and developing many problems common to the geriatric......

Words: 662 - Pages: 3

St Dimas Living Facility Project 2

...Introduction St. Dimas is looking to halt its ever slowing profit margins by building a brand new assisted living facility or ALF on its campus. It has been struggling in recent years with declining facility enrollment and is looking to adapt its business practices to compensate for this loss. In this paper, I will discuss the viability of this proposal. I will define the project deliverables, constants and assumptions. Perform a Level 1 WBS and speak to Dr. Splient’s abilities as a viable project manager. Analysis The analysis of the proposals from Dr. Splient’s team will help define the project deliverables amongst the team. “Whenever you have a new project (either created/identified by you or assigned to you), one of the first things you should do is define the deliverables for the project. The deliverables on a project are the specific work products that you have to produce in order to complete the project,” (Perman, 2009).There is a two month timeline for the completion of this part of the project as the entire project is rushed due to the needs of St Dimas and their need to finish before the summer or July 2000. There are several people responsible for their different parts of the project. The Construction Project Manager has the responsibility of construction. The COO will oversee design and logistics of food services, housekeeping, staffing, and policy and procedure development. The CFO will manage budgets for all of the projects and create payroll and......

Words: 1061 - Pages: 5

St. Dismas Assisted Living Facility Case Study.

... | TABLE OF CONTENTS 1 INTRODUCTION 3 1.1 Purpose of LITE Project Charter 3 2 project And Product Overview 3 3 Alternatives 3 4 Scope 3 4.1 Objectives 3 4.2 High-Level Requirements 3 4.3 Major Deliverables/Milestones 3 5 Duration 3 5.1 Estimated Timeline 3 6 budget Estimate 3 6.1 Funding Source 3 6.2 Estimate 3 7 project Charter approval 3 APPENDIX A: REFERENCES 3 APPENDIX B: KEY TERMS 3 Introduction 1 PURPOSE OF ST. DIMSS ASSISTED LIVING PROJECT CHARTER THE ALF PROJECT CHARTER DOCUMENTS AND TRACKS THE NECESSARY INFORMATION REQUIRED BY DECISION MAKER(S) TO APPROVE THE PROJECT FOR ASSISTED LIVING FACILITY. The intended audience of the ALF Project Charter is the project committee and senior leadership. project requirement THE PROPOSED PROJECT WILL PROVIDE THE STEERING COMMITTEE WITH ESTIAMES TO EXPAND ST. DIMISS MEDICAL CENTER BY ADDING AN ASSISTED LIVING FACILITY. Alternatives PRIOR TO INITIATING THIS PROJECT 4 ALTERNATIVE SYSTEMS WERE REVIEWED AND A GAP ANALYSIS CONDUCTED TO VERIFY IF THEY WOULD BE CANDIDATES FOR USE. a. Healthimpact.net – System used for Budgets and did not meet the searchable requirement necessary to make project successful. Therefore, Healthimpact.net cannot be used. b. IRB Online – Used for tracking and approval of protocols through the IRB process. Protocols are outputs of projects and not all......

Words: 1123 - Pages: 5

How to Run an Efficient Assisted Living Facility

...In the comfort of your home, of course. Sandy’s Elder Care or (Assisted Living Facility) strives or (endeavors) to be that home for 4 full-time assisted living residents, offering medically-skilled care in a respectful, self-sustaining community. In our facility, residents will receive services from individuals with decades of experience in the medical and education fields as well as alternative visions of the potential in our elderly family members' latest years. In our first five years, we will establish a new kind of Elder Care model based on the idea that the elderly are fully-realized persons, with ideas, thoughts, and experiences which matter. Can you help us to realize this goal? 1.1 OBJECTIVES Financial: For our first year, we have four financial objectives: * To raise adequate funding for start-up. * To open the facility, and maintain it at 3 to 4 rooms occupied each month. * Begin development implementation for the ongoing funding needs of years two through five. Non-financial * To provide a warm, comfortable, safe and engaging home for up to 4 permanent residents. Ongoing feedback through the residents, family members of the residents and volunteers will give us a weekly update on our progress. * To provide adequate training, mentoring and compensation to our caregiving staff to create job satisfaction. 1.2 MISSION At Sandy’s Elder Care or (Assisted Living Facility), we promote the dignity and self-worth of all of our residents...

Words: 780 - Pages: 4

Overview of Asssted Living Facilities

...Overview of Assisted Living Facilities Richard Brady BUS 620 Managerial Marketing Prof. Debra McCoskey-Reisert August 25, 2014 After reviewing several industries for this assignment, I chose the health care industry, specifically the Assisted Living portion. This industry right now is a very dynamic one with a lot of changes occurring on a consistent basis. Hence the ability to use an analysis tool would allow a good look into the potential of this industry. Finch explains in the text, that the information gathered when using a analysis or from an environmental scan “systematically assesses how elements of the external environment will impact a business or market.” It also “provides managers with relevant information to improve the quality of marketing decisions.” The analysis that will be used, is the PESTEL model which identifies six different external factors that could affect a business, political, economic, social, technological, environmental, and legal. Political influences on Assisted Living would include any federal restrictions that have been implemented. The biggest variable however, would be the state regulations. Assisted Living is currently regulated by each individual state. This makes doing business in multiple states a little confusing, and frustrating because you have to be familiar with each state’s expectations. When a state auditor comes to inspect your facility in Washington, there will be different expectations than when an audit is......

Words: 1267 - Pages: 6

St Dismas

...Week 6 Discussion For the Week 6 Discussion you will create a Gantt chart for one element of the St. Dismas case study project. Using a project management tool like MS Project is typically the easiest and fastest way to do this. However, it is not the only way. You can use MS Office products as well to create the Gantt Chart. Students often ask about the use of project management software applications in this course. In the past we required the use of MS Project for this course but removed it as a requirement when we rewrote the course. The reason we removed it was that MS Project has a very steep learning curve for all but the most basic functions. The software is very expensive and is not web-based so it requires installation on your computer. This posed many issues for our students. In this course the assignments were designed so that students could complete them without using any project management software at all. For example, the WBS can be done using MS Word, EXCEL, PowerPoint, or VISIO. The same is true of the Gantt chart and network diagram although it does take more time to do them this way than it would if you used software that automatically draws the Gantt and network diagram from the WBS. There are a number of free tools and helpful websites available for creating project Gantt Charts. Here is a sample you might want to explore. How to create a Gantt Chart in MS......

Words: 1298 - Pages: 6

Case Study on Assisted Suicide

... physician assisted suicide, and palliative sedation. In euthanasia, the doctor administers the drug to end life. In physician assisted suicide, the doctors prescribes the patient with the drug and the patient administers it on their own free will. Palliative sedation is the major gray area. Doctors have the responsibility to keep terminally ill patients comfortable and limit suffering. The means utilized to assist with sedation, also helps in the passing of the patient peacefully (Boudreau 3). My father was terminally ill from a bone marrow cancer. He was already on a main course of sedatives, but still in immense pain. I was by his side when the doctor said he was going to give my father the maximum amount of morphine allowable. He said it would ease his pain, it will slow his heart rate, and he will probably pass peacefully. It took maybe an hour. His heart rate slowed, and he passed as if he was sleeping. I was very thankful the doctor was willing and able to do this. Was it physician assisted suicide? Not at all. The cancer killed my father. Question #6. There should be a lot of restrictions on assisted suicide. The first and foremost would be the requirement to go through several counseling steps that might help the person deal with the situation in a different manner. Works Cited Ghillyer, Andrew, and Andrew Ghillyer. Business Ethics Now. New York, NY: McGraw-Hill, 2012. Print. Boudreau, J. Donald, and Margaret A. Somerville. "Euthanasia And Assisted Suicide: A......

Words: 570 - Pages: 3

St. Dismas Assisted Living Facility

...St. Dismas ALF Assignment #3 1. Draw a Gantt chart for the construction phase of the program. What is the completion date if construction starts in March? What is the completion date of the project if construction is started in November? If the project is started on March 1st, 2012, the finish date is July 30th, 2013. For the November start date, the case does not mention exactly what date the project should start but rather mentions that it should start after the elections. We do not have the election date so I will assume a start date of November 14th, 2011, which is a Monday. In this case, the end date of the project would be April 11th, 2013. However, the case states that if the project starts in November, bad weather could affect the outside operations, adding as much as 2 months to the duration. If we add 2 months to phase 1, the entire project is delayed 2 months. However, if the delay only occurs in phase 2, than the end date of the project would not be affected since no tasks have phase 2 as a predecessor. This is quite unlikely since it would impossible, in real life, to proceed to phases 3 and 4 (Enclosures and Interiors) without first completing or at least having a certain percentage completed of phase 2 (Structure). For this reason, I choose to add 2 months in phase 1 and therefore have a new end date of July 4th, 2013. Please note that I have also considered that the 2 months delay include the Christmas and New Year holidays. Gantt charts...

Words: 1117 - Pages: 5

Lecture 05 -Case Study (1)

...St. Dismas Assisted Living Facility Case 1: Planning the Project St. Dismas Medical Center, an urban, nonprofit, 450 - bed rehabilitation hospital began to see a significant decline in admissions. St. Dismas’ mission focuses on inpatient and outpatient rehabilitation of the severely injured and catastrophically ill. While the patient census varied from month to month, it appeared to the St. Dismas Board of Trustees that the inpatient population was slowly but steadily declining. The hospital’s market researchers reported that fewer people were being severely injured due to the popularity of seat belts and bicycle/motorcycle helmets. In order to get a handle on the future of the organization, the Board, and the CEO, Fred Splient M.D. called for a major strategic planning effort to take place. In January 1999, St. Dismas held a planning retreat to identify future opportunities. The outcome of the retreat was that the Medical Center needed to focus its efforts around two major strategic initiatives. The first, a short run initiative, was to be more cost - effective in the delivery of inpatient care. The second, a long- run strategy, was to develop new programs and services that would capitalize on the existing, highly competent rehabilitation therapy staff and St. Dismas’s excellent reputation in the region. At the time of the retreat, Fred Splient’s parents were living with him and his family. Fred was an active member of the “sandwich generation.” His parents were aging and......

Words: 1608 - Pages: 7

St Dismas Assisted Living Facility -- 1

...concurrent engineering. Cases and Readings Some cases appropriate to the subject of this chapter are: Harvard: 9-692-058 Taco Bell Corp. This 31-page best-selling case describes a project to implement a new strategic plan involving major changes in layout, staffing, quality, product design, and information systems. The coordination and integration of all these project activities is what makes the plan successful, and hard for competitors to imitate. Two teaching notes are available for this case: 5-692-091 (20 pages) and 5-196-073 (12 pages). Harvard: 9-694-059 Hardcard Project: Plus Development Corp. (A1); 9-694-060 Hardcard Project: Plus Development Corp. (A2) This 10-page (12-pages for A2) case allows the students to evaluate, using Microsoft Project software, the time line, resource allocations, and other aspects of a major project concerned with developing a hard disk drive. The perspective is from that of the VP of engineering. The (A2) case updates the project and the students have to determine whether a specific market introduction date will be feasible for the project. (Note: this case duplicates some of the information in the Plus Development Corp. case suggested for Chapter 2.) Harvard: 9-193-013 American Airlines: The InterAAct Project (A) and 9-193-014 (B) This 17-page (and 11-page) set of cases describes the design and implementation of an extensive knowledge information system project. The implementation is in trouble in the (A) case and......

Words: 3681 - Pages: 15

St. Dismas Case Study

...1. St. Dismas case study – part 5 on page 267, answer the questions (4 points) QUESTIONS 1. What do you think the construction project manager should have done when the Director of Security stopped attending the project meetings? Tracked him down and explained that absence was not an option. Elevated it to Fred if it continued for another week. Frank has to figure out how to get coverage – that is why he is the director of security 2. Do you think it is an effective communications tool to send the construction project meeting minutes to the ALF steering team and the President? Support your answer. It is necessary, but only effective if people react to it – Kyle should have realized long ago, that that was not the case and followed up verbally. 3. How much time has to be made up for the original, baseline schedule to be met? 14 days 4. Develop an action plan and draw a Gantt chart for the Parking Lot phase of the project as originally planned by Kyle. Answer Fred's questions. The parking lot plans were not in the original plans because Kyle thought they would not impact the overall completion date If the approval does not come through until May 1, then the completion will be delayed to June 12. We can afford to wait until May 4. 5. What information does Fred need to make a decision about building a hair salon? The potential income, what it will cost to change the plans to accommodate it and how it will affect the schedule. Individual part 2. Do problems 25...

Words: 553 - Pages: 3

St. Dismas Assisted Living Facility Project Action Plan -- 3

...1. Draw a Gantt chart for the construction phase of the program. What is the completion date if construction starts in March? What is the completion date of the project if construction is started in November? If the project is started on March 1st, 2012, the finish date is July 30th, 2013. For the November start date, the case does not mention exactly what date the project should start but rather mentions that it should start after the elections. We do not have the election date so I will assume a start date of November 14th, 2011, which is a Monday. In this case, the end date of the project would be April 11th, 2013. However, the case states that if the project starts in November, bad weather could affect the outside operations, adding as much as 2 months to the duration. If we add 2 months to phase 1, the entire project is delayed 2 months. However, if the delay only occurs in phase 2, than the end date of the project would not be affected since no tasks have phase 2 as a predecessor. This is quite unlikely since it would impossible, in real life, to proceed to phases 3 and 4 (Enclosures and Interiors) without first completing or at least having a certain percentage completed of phase 2 (Structure). For this reason, I choose to add 2 months in phase 1 and therefore have a new end date of July 4th, 2013. Please note that I have also considered that the 2 months delay include the Christmas and New Year holidays. Gantt charts of both start dates (including the...